Hi All,

We confirmed a problem when we performed "clean up" of the Master/Slave resource in Pacemaker1.0.
When this problem occurs, "probe" processing is not carried out.

I registered the problem with Bugzilla.
 * http://bugs.clusterlabs.org/show_bug.cgi?id=5211

In addition, I wrote the method of "clean up" avoiding a problem for Bugzilla.
But this method may not be usable depending on the combination of resources.

I request improvement if I can revise this problem in Pacemaker1.0 in community.

 * But this problem is improved in Pacemaker1.1 and does not seem to occur.