[Pacemaker] manage/unmanage and stop/start logic

Dejan Muhamedagic dejanmm at fastmail.fm
Thu May 20 05:05:01 EDT 2010


Hi,

On Wed, May 19, 2010 at 03:35:26PM -0400, Vadym Chepkov wrote:
> There is some flow in start/stop and manage/unmanage logic in
> the crm, in my opinion.
> 
> For example,
> 
> I unmanaged some resource to do maintenance, then I issued crm resource manage again.
> At this point crm will add  meta is-managed="true" to the resource.
> 
> Later on I need to upgrade pacemaker software
> so I issue 'crm configure property is-managed-default=false'
> and all resources will be unmanaged except those that I was "managing" before.
> so I have to go into each individually and remove meta is-managed.
> 
> And basically the same problem with target-role.
> 
> maybe the logic should be changed and not to add a redundant meta? If the result can be achieved without adding meta don't add it?
> And add only if we add "force" option, for exampe?

Too late for that, we shouldn't change semantics. I did think
about it at the time and say "resource manage rsc" seemed
unequivocal. BTW, there's a way to remove a meta attribute:

crm resource meta <rsc> delete <attr>

Thanks,

Dejan


> Just a thought.
> 
> Vadym
> 
> 
> 
> _______________________________________________
> Pacemaker mailing list: Pacemaker at oss.clusterlabs.org
> http://oss.clusterlabs.org/mailman/listinfo/pacemaker
> 
> Project Home: http://www.clusterlabs.org