On 2008-01-26T21:29:39, Andreas Mock <Andreas.Mock at web.de> wrote:

> the crm.dtd says about the "ordered"-attribute:
> -------------------------8<--------------------------
> ordered 
>     * Start (or stop) each clone only after the
>       operation on the previous clone completed. 
> -------------------------8<--------------------------
> 
> Does anyone know if this is also true for monitor action?

No, monitors are independent from each other. They also don't receive
the notify attributes (nor are pre/post notifies sent for them) - that
would be too much effort to synchronize and replicate.


Regards,
    Lars

-- 