[Pacemaker] Ordered attribute of clone resources
Lars Marowsky-Bree
lmb at suse.de
Sat Jan 26 20:40:38 UTC 2008
On 2008-01-26T21:29:39, Andreas Mock <Andreas.Mock at web.de> wrote:
> the crm.dtd says about the "ordered"-attribute:
> -------------------------8<--------------------------
> ordered
> * Start (or stop) each clone only after the
> operation on the previous clone completed.
> -------------------------8<--------------------------
>
> Does anyone know if this is also true for monitor action?
No, monitors are independent from each other. They also don't receive
the notify attributes (nor are pre/post notifies sent for them) - that
would be too much effort to synchronize and replicate.
Regards,
Lars
--
Teamlead Kernel, SuSE Labs, Research and Development
SUSE LINUX Products GmbH, GF: Markus Rex, HRB 16746 (AG Nürnberg)
"Experience is the name everyone gives to their mistakes." -- Oscar Wilde
More information about the Pacemaker
mailing list